About this feature

Priority zones tell SchedOpt which areas should be mined earlier when multiple blocks are feasible. You import a CSV of zones, assign priority values against the pit design, and confirm the zones display correctly before optimisation.

Use a simple priority scale (for example 1 = highest) and keep it consistent across scenarios.

Step by step

  1. Prepare a priority zone CSV in the expected format.
  2. In SchedOpt, choose Import Priority Zone.
  3. Select the *.csv file.
  4. Enter or map priority values for each zone on the pit design.
  5. Visually confirm zones overlay the correct blocks.
  6. Save and run a test schedule if desired.