Import pit blocks, dump blocks and roads
Bring AutoDesign solids and haul roads into SchedOpt and set up plant and stockpile destinations.
About this feature
SchedOpt scheduling starts from mining and dump solids plus a road network. This tutorial imports pit blocks, dump blocks and roads from AutoDesign, then adds plant and stockpile destinations so material can flow through the schedule network.
Fix import warnings before you tune period capacities — bad geometry produces hard-to-debug schedule failures.
Step by step
- Open SchedOpt → Block (or the import page).
- Import pit blocks, dump blocks and roads from AutoDesign.
- Review counts and extents after import.
- Add Plant and Stockpile destinations.
- Create or confirm links/roads between sources and destinations.
- Save before setting period parameters.